Date/Period | Event | Remarks/Ref | ||
June 2009 | Boulevard - OMR Project commenced by Ceebros Builders | Land taken from AKDR Group | ||
June 2012 | Project completed - First of few families occupied. JLL appointed as Maintenance Company. | Association formed by select few. They obtained all the powers and formalities from the builder. | ||
June to Dec. 2012 | Maintenance and Management Mechanism Created | The select few apportioned the tasks to themselves. A person assumed the task of account service providing. After hardly few weeks of living, he left the apartment. But remained 'account service provider' - Never introduced, never ever informed to later committee members. | ||
Dec. 2012 | *** ** was looking for a apartment in OMR | Stumbled upon this project in casual conversation with a flat seller. After some efforts, identified a flat to let and entered this apartment as 'Tenant' since Jan-2013. | ||
Jan-2013 | After proper intimation an EGM was conducted. Well attended by Owners and Tenants. There was maintenance arrears for previous quarter. Cleared by *** **. |
| ||
Jan-2013 | One payment for previous quarter paid by cheque. | Pre-Printed serial numbered receipt obtained. | ||
Jan-2013 | Approached office to make current due maintenance payment | Accountant informed 2 dues Total Rs.27000 pending. After producing Pre-printed serial numbered receipt and cheque pass detail (cheque was passed 10 days earlier) entry was updated. | ||
Jan-2013 | Notice Board information. To save paper and to environment, no paper receipt will be given. Cheques to be dropped in drop boxes. No personal visit to office by resident (to save accountant time) | Personally protested to Mr.Kishore Panicker. Explained previous incident in which the accountant could update record only after producing pre-printed receipt. Informed Mr.Kishore, for apartment society, issuing proper serial numbered receipt is mandatory. Save paper attitude is not correct. Insulted by Kishore, that I need to talk to owner only. | ||
Apr-2013 | Notice Board Information. If maintenance not paid within 15 days, DG backup will be cut. | Pre-printed paper receipt practice stopped, cheque payment not updated, I decided to pay by credit card. Went 3 times to make payment (taking off from office work). 1st time accountant was not available. 2nd time credit card machine was locked in a drawer and key was not available. 3rd time person knowing credit card swipe not available. I could not pay within due date. | ||
Apr-2013 | My DG backup was cut for non payment of maintenance. | Contacted then president Mr.Kannan. Curtly informed that, 'talk to your owner'. Bluntly insulted with additional remark, 'Tenants do not have right to speak!'. After registering my protest through E-Mail (record available), clearly mentioning that, "Maintenance due is billed only for current and future period, disconnecting a essential service (Power backup) for non payment is illegal (billing period itself is in future), I paid the maintenance and bought peace. | ||
Year 2013 | Found several postings in apartmentadda deleted or manipulated. | No proper communication about who moderating. | ||
Year 2013 | Some suggestions given for betterment of residents. | All ignored, with a common remark, 'you become owner and become committee member and do it yourself! In our busy schedule we can give only this much attention'. | ||
May-2014 | I became owner, volunteered to become committee member. | Volunteered to become committee member to do my bit of service to the community where I live, and to help reduce the workload of others. | ||
May-2014 | Claiming resident owners are not participating, an opinion was sought about including Non-Resident Owners into Management committee of Association. | |||
July-2014 | AGM held, new committee members chosen | After scrutiny 15 members including me accepted as Committee members. When apartment adda was suggested as 'Only Medium' to make payments, I protested stating, 1) It can be additional medium, 2) It is run by private, if they close the company and run away, who will go after them to collect money paid by residents. | ||
July-2014 | AGM held. Resolution passed on voice vote accepting accounts ignoring protest by some. | Account submitted showed an entry, 'Amount siphoned off' and close to Rs.1.65 Lakh was shown. On specific enquiry by a lady member, it was explained that a staff collected cash and ran away. Since he is from Kannagi Nagar, he may come with nearly 2000 persons and create nuisance, no action taken. When some members insisted to take action, they were told, 'you become committee member, and do yourself'. A standard usual phrase was repeated, 'anyone can come to office and see any records they want at any time. Full co-operation will be given!' | ||
July-2014 | first committee meet that I attended. | It was on Sunday in perfect Raghu Time (I preferred to go before 4:30 pm). Too casual meet. No one made introduction or self introduction. No stationery or Pen provided. President came late clad in half trouser and banian, murmured something and declared the meeting over. I offered help in account maintenance (as I had previous bad experience), President said, 'yes, no problem!'. | ||
July-2014 | Chance encounter near Hindu office | An old acquaintance met me. After initial talks, he wanted leads for large cooking gas consumers like our apartment society. I told him ours is an apartment of nearly 350 flats with piped gas supply and all are residential. He told me, "We will supply at Domestic Rates to all Without any KYC docs (self certification by dealers) and will improve upon whatever existing cost of purchase". He just wanted the info about at what rate we buy gas. | ||
July-2014 | 1st email, 1st enquiry | Remarks/Ref - Detailed in this PDF | ||
Aug-2014 | Thinking about Resigning | Very quickly (may be earlier than many of you) I decided. 1) This association is run by innocent people who do not know how to manage it; OR 2) By cunning clever people who are corrupt and efficient in deviating and diverting the issues. | ||
Aug-2014 | Closed meet with select members | At the initiative of Mr.Ravikumar & Mr.Kamlakar (I am very sure, both are broad minded generous people with no iota of doubt, clean hand and clean heart people - Unfortunately they were cleverly manipulated to hate and turn against me) a close meet took place in which President and Secretary listened to me patiently. They agreed to give importance to my view points. Earlier I circulated 'Areas of Concern Document. It was read and appreciated. | ||
Sep-2014 | Lady member resigned | Suddenly received a email from Secretary that a lady member (who was very active till previous day and sought my assistance to prepare gardening contract draft) resigned and replaced. I asked for resignation document. Nothing was produced for nearly a month. | ||
Oct-2014 | I resigned | Nearly after a month (of lady member resignation) a selective portion of email communication given to me. It was clear that the email was just (one month later after replaced) dated. When I pointed it out, 'Secretary offered to resign, President Offered to resign, other members offered to resign'. In order not to hurt them, I resigned. | ||
Oct-2014 | 1st Meet about Corruption charges - I did not attend | By now, I became sure that; This association is run by But I decided not to attend the meet because, 1) I did not like to expose corruption in open forum with un-deniable evidences that may lead to a panic situation wherein culprits may stop water supply, gas supply etc., overnight and point finger at me as root cause; 2) I still wanted to give a chance for reform, allow the wrong doers admit mistake in private and do corrective steps. | ||
Oct-2014 | ceebrosboulevard.com born | Having proven to many that apartmentadda based ceebros boulevard forum is manipulated, I created online presence. But I limited that to static pages. | ||
Jan-2015 | 2nd meet about Corruption Charges - I attended | Even though I was busy, left alone, let alone, felt defeated, insulted, I walked out of all the thoughts. As many people mentioned in apartmentadda forum that I seek publicity, I REMOVED MY KNOWN NAME in all posts. By now I am sure, 4 are corrupt. But they are clever enough to shout and divert the anger of all others against me. I attended this meet, offered reasonable explanation of my stand. I was threatened not to take notes of the minutes. I was threatened of assault. In a hall of 60 persons, I was let alone. About 50 people were against me. 20 of them aggressive towards me. 10 of them were sympathetic with me. None of them were supportive of me (I leave out a handful who supported me in private and expressed their inability to support me in public) | ||
Jan-2015 | Shifted as tenant | For personal reasons I shifted flat and became a tenant. | ||
Dec-2015 | Became owner - But prefer to identify as tenant | I bought another flat and became owner. That is let out. I prefer to remain tenant and be treated as tenant. | ||
Jan-2016 | Event - Flood relief forced collection | The flood relief forced collection drive, and disconnecting power backup to non-payers forced me to revisit these pages and make them interactive contents in the form of this blog. |
CEEBROS BOULEVARD is arguably a best gated community in OMR, Chennai. It has all the comforts of a great gated community. But ...